Rebuilding Program: Foundation Pouring
After months of obstacles and problems, we managed to pass our first five inspections for our temple rebuilding. On November 6th, we had 31 concrete trucks coming and going as we poured 167 cubic metres of concrete to complete our foundation slab.
The pictures below are over several days with the preparation of the bored piers, pouring concrete for the piers, setting up the slab steel and pouring the slab.
Our project leader, the first to step on the concrete, celebrating having put Vimokkharam’s future on solid foundations.